雙語 | 蓬萊站:萬華新材料低碳產業(yè)園項目

來源:膠東在線  2023-02-08 15:07:00
A+A- |舉報糾錯

  蓬萊站 | “萬華新材料低碳產業(yè)園”項目:一二期壓茬同步實施,萬華項目主打“快”節(jié)奏

  Wanhua New Material Low-carbon Industrial Park:Phase I and Phase II Simultaneously Implemented under Fast Pace

  萬華新材料低碳產業(yè)園項目由萬華集團投資建設,總體規(guī)劃11.48平方公里,建成投產后年產值1800億元。計劃分三期實施,其中,一期占地2.21平方公里,主要建設高性能新材料一體化等項目,生產丙烯及乙烯下游產品。

  The project is invested and built by Wanhua Group with a total planning area of 11.48 square kilometers. The expected annual output value after completion is 180 billion RMB. It will be implemented in three phases, the first phase of which is planned to cover an area of 2.21 square kilometers, mainly for the construction of high-performance new materials integration project and the production of downstream products like propylene and ethylene.

  一期工程以世界頂級規(guī)模丙烷脫氫為龍頭,下游包括環(huán)氧丙烷裝置、丙烯酸及酯裝置、聚醚裝置等;并通過長輸管線實現與萬華煙臺工業(yè)園的物料互聯互通。一期工程是2022年和2023年省重大實施類項目,于2022年3月開工建設;目前,維修站辦公樓、地源熱泵系統、維修車間已投用,綜合倉庫主體結構完工,116臺長周期設備訂貨完成;計劃2024年6月中交,達產后年產值270億元。二期工程是2023年省重大實施類項目,計劃2023年上半年與一期工程壓茬同步實施。

  Phase I takes the world's top-scale propane dehydrogenation project as the leading part, and downstream projects include epoxy propane units, propylene acid and ester units, polyether units and so forth, which will be interconnected with the Wanhua Yantai Industrial Park through a long-distance pipeline. Phase I project is a significant implementation project of Shandong in 2022 and 2023, whose construction began in March 2022. Currently, the office building of maintenance station, geothermal heating system, and maintenance workshop have been put into use. The main structure of the comprehensive warehouse has been completed, 116 orders of long-cycle equipment have been placed, and 1 billion RMB has been invested. The completion of the project is due in June 2024 and the expected annual output value after reaching full capacity is 27 billion RMB. The Phase II Project is a significant implementation project of Shandong in 2023 and is planned to be carried out in the first half of 2023, in parallel with the Phase I Project.

初審:李里
復審:王大鵬
終審:孫玲姿
新聞爆料:QQ群 41885496  熱線 8200999

相關新聞
下載煙海e家
映像膠東更多
視聽中心更多

煙海e家   簡介:提供新聞資訊、黨務政務、民生服務、身邊互動等服務。

煙臺公交客戶端   簡介:隨時隨地查詢公交運行位置,到點準時來接你,等車不再干著急。

膠東在線版權所有

網站簡介網站地址標識說明廣告服務聯系方式法律聲明違法和不良信息舉報中心